Programming joinery on a live build: first fix, second fix and delivery windows

Joinery sits across the programme, not at one point on it. Some elements go in early and are buried by the work that follows; others are installed near the end and decide whether a building is ready to hand over. Planning around both is the difference between a smooth finish and a squeezed one.

First fix joinery

First fix elements, such as door linings, frames, structural timber details and carcassing for built-in work, go in before plastering and decoration. They need to be ordered and made early, and they depend on accurate setting out. Decisions about door positions, panelling set-outs and services routes must be made before this stage, not during it.

Second fix joinery

Second fix covers doors, architraves, skirtings, fitted furniture, panelling and staircase finishing. It follows plastering and, usually, is installed before or alongside final decoration. This is where the programme tends to tighten, because many trades want the same rooms at the same time.

Make time and lead time

A workshop needs time to draw, gain approval, order timber, make and finish. Our work typically runs from about six weeks for smaller items to around six months for large projects, depending on scope. Ask for a programme that shows drawing, approval, making, finishing and installation as separate stages, so you can see where float exists and where it does not.

Delivery windows

Give the workshop a delivery window, not just a date, and tell us about access, storage and protection. Joinery should arrive when the building is dry and ready to receive it. Delivering too early risks damage and movement; too late costs the programme.

What keeps a programme honest

  • Approved drawings by an agreed date.
  • Frozen dimensions at an agreed date.
  • A named person on site to receive and sign for deliveries.
  • A clear route for decisions when something changes.

If you are planning a package and want to talk through sequence, our page for builders and contractors is the best place to start.

How long does bespoke joinery take to make?

It depends on scope. Smaller items can take around six weeks, while large whole-house projects can run to around six months. A programme showing drawing, approval, making, finishing and installation stages is the most reliable guide.

What is the difference between first fix and second fix joinery?

First fix is the structural and concealed timberwork installed before plastering. Second fix is the visible finishing joinery installed after it, such as doors, panelling, skirtings and fitted furniture.